Common Agile Practices That Sabotage Us


Sometimes we need help to improve our team and sharing insights into why some practices and behaviors can sabotage team progress.  Take a look at the following observations teams have made to see if your team can identify with them and take action before it becomes a bigger or longer term problem.

Observation:

We have a lot of stories that are closed by DEV and then new stories for QA testing are created to test what Dev hands over.

Impact to the Team:

  • Because the number of stories in the sprint steadily increase during the sprint, the burndown chart will likely look like the team is always behind schedule.
  • Individual capacity is extremely difficult to plan during sprint planning because the number of stories at the beginning of the sprint will be lower than reality.
  • Forecasting sprint plans and project schedules via velocity is useless here because the…

View original post 988 more words